The request will allow Evergy Inc. to rebuild and expand its electric substation located on property along the south side of SW 6th Avenue between SW Golden and SW Highland. "Public Utility Facilities, Type II" require a Conditional Use Permit in this X-1 district and in most other zoning districts. Evergy applied for "PUD" zoning in order to allow heights up to 75 feet, exceeding the 62 foot height limit in the zoning code.
The site has contained an electric substation since 1981 and is a non-conforming use under the current "X-1" zoning. The substation has to be rebuilt to maintain and improve service in the area. The modifications necessitate expansion of the substation on to property immediately east containing an automobile repair business, which is also a non-conforming use that has remained since 1977.
The applicant was not required to conduct a neighborhood information meeting due to circumstances of COVID-19, although at direction of the Planning Department the applicant mailed notices to all property owners within 300 feet of the site.
The Planning Commission recommended APPROVAL by a vote of 7-0-0 at the October 19, 2020 public hearing as indicated in the attached minutes. The Planning Dept. recommended APPROVAL as indicated in the attached staff report.